Braunschweig Municipal Hospital

As part of the construction of the new clinic dialysis unit, we were awarded the contract to design and implement our Smart Dialysis solution.

Klinikum Braunschweig Ansicht des Gebäudeteils Ost
Share post

Implementation: 2023/2024
Solutions in use: HE.RO: here with connection to district heating, GreenTec Performance System (GPS) Smart Water, Smart Energy

Description of the project

The decision-makers launched a public tender as part of the new clinic dialysis construction, seeking a partner for the water technology concept.
We proposed a concept that is as sustainable as possible while optimizing operating costs. Together with B. Braun, we were awarded the contract.

Our services as GreenTec Dialysis GmbH:

We implemented our Smart Dialysis concept which includes Cross-Sector Integration, here with our HE.RO system and connection to the existing heating infrastructure, as well as our GPS (GreenTec Performance System) for control and monitoring. Additionally, we installed a single-stage reverse osmosis combined with a hygienic hot cleaning system, a permeate ring line and a concentrate mixing system, all integrated into our Smart Dialysis® concept.

Our self-developed product “CPG” (Chlorine Protection Guard) measures the chlorine levels in drinking water according to DIN EN IS0 23500. It removes chlorine using an activated carbon filter and triggers an alarm if the chlorine level becomes too high. Chlorine damages the membrane on reverse osmosis systems and, in some cases, reach patients. This poses a risk that must be avoided.

Clinic dialysis presents unique challenges. To address these, we combined various interfaces, such as medical technology and medical gases, into a custom-designed media rail.

We call the combination of Cross-Sector Integration and our GPS “Smart Dialysis®”. This smart approach enables our customers to save costs while using less energy and water. It brings us closer to the goal of green dialysis.

Das Portraitfoto zeigt Prof. Dr. Jan T. Kielstein von vorn.

Umsetzung: 2023/2024
Eingesetzte Lösungen: HE.RO mit Anschluss an Fernwärme, GreenTec Performance System (GPS) Smart Water, Smart Energy

Über unseren Kunden

In der zertifizierten nephrologischen Schwerpunktklinik werden pro Jahr ca. 16.000 Hämodialysebehandlungen durchgeführt.

Projektpartner

B.Braun; www.bbraun.de

For further Information:

Christian Rohde
CEO / Sales & Project Management / Partner

Further references

Reference

Kidney Centre Stuttgart Vaihingen

"The modernisation during ongoing operations was a challenge for everyone. The collaboration with GreenTec worked perfectly. We were not only able to create additional treatment places, but also save resources and thus increase the ecological and eco… ...

Scroll to top
We are a member and support Startup Verband e.V. DGAHD e.V. Industriekuratorium Deutsche Gesellschaft für Neprologie ZUKE GREEN leaders for climate action nafasi BNW Bundesverbend Nachhaltige Wirtschaft e.V.